Under the Inter-Agency Task Force (IATF) guidelines on enhanced community quarantine, energy companies and their 3rd party contractors are exempted from travel restrictions.
PALECO acting general manager and project supervisor Engr. Nelson Lalas said PALECO is negotiating with DMCI to have four megawatts installed in Roxas while seven megawatts will be installed in Brooke’s Point.
NARRA, Palawan -- Amidst pressure from opposing sides on the planned construction of a coal-fired power generation facility here, the town’s newly-elected mayor said Wednesday he will await the outcome of a public consultation process he had initiated among his constituents and will decide on his course of action.
The issuance by the Department of Environment and Natural Resources (DENR) of an environmental compliance certificate (ECC) to the coal-fired power plant facility in...